Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
  • TWS-33 : Joel and Frank are working on setting up an XAMPP development environment for working on it
    • Joel is having problems getting PHP working correctly, the calendar is not currently being displayed
  • When replaying the library information, do not make it a hyperlink, just text that says "check location schedule"
    • Only schedule icon and navbar would be used to access the schedule page
  • Joel is starting to fall behind on his expected work completion schedule
  • TWS-42 : work still in progress.   This should fix bug TWS-62
  • TWS-41 : still needs to be looked into
  • TWS-47 : still need to place it on the correct spot on the page and add the "Check Schedule" label to it
  • Lora has a pick list text file with all the library/meeting information for when she does the weekly schedule updates
    • Lora is the only person who can make these updates.
    • It requires access to a password protected account and the password is NOT available to TSSG members
  • TWS-43:
    • Test steps from one of the test runs was removed after the run was completed and a bug was reported against a test step
    • This should NEVER be done once a test run was executed and a defect reported against it
  • You need to go into TWS-43 to get to the test set for the different test cases created for the test scenarios
  • Team went over Jay's email about UI and UX
    • This will need to be taking into consideration when we work on TWS-32
  • No second full team meeting this week