Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Paul - did not participate in the sprint so no feedback


Tom - no feedback


Tyler

  • Generally went well
  • Had a short training on X-Ray, but did not cover enough for creating test cases and test executions
  • Test executions were not showing up in the common board, should they appear there?
  • At some point, needs to present Google Analytics to team.  Need to decide when this will be done.
  • Working on getting the plug-ins into Edge so he can test more devices (broader coverage)
  • Rather than making the sprint longer, could put less stories into the sprint to keep them shorter


Wayne

  • Well - We accomplished our goals for this sprint!
    • LOTS of collaboration
  • Not well-
    • We went one week over our time box, but we expected that to happen and should plan for more time in Sprint 3 to avoid going over again
    • We want to do Agile but do not want to follow Agile practices
    • Story status, not person status - did it work better?
  • Improve:  The entire team needs training on how to properly use the X-Ray plug-in in Jira to create test cases, test executions, report defects, and test fixes to defects


Discussion:

  • Team needs to decide more time OR less stories in the sprint
  • Need to have a Ready To Test to the Jira workflow for Sprint 3
  • If people come in late, do a "this is what we are doing" when we move to next person rather than stop and catch that person up