Three questions:

  • What went well this sprint?
  • What did not go well this sprint?
  • What do you want to see changed/improved in the next sprint?

No debating items during each person's feedback, we will talk about issues after everyone has given their feedback


Frank

  • No feedback


Joel

  • Went well - got a decent amount of output with help from other developers in the group
    • Started using PHP, then switched to Javascript after security concerns were raised
    • Shared code through GIT
    • Using Jira to track status and testing had some learning pains but overall went well
  • Not well - went overtime with meetings
    • Some issues with testing
    • Some delays in getting work accomplished, took longer than expected


Jim

  • Was out for 2 weeks of the sprint, so was a remote observer for most of it
  • Most of the problems the team hit were things we need to tighten up so we have a better process in place
  • Went well - a lot of independent thinking and figuring out of things, lot of collaboration
  • Not well - spent more time than we wish we would to nail down the processes we wanted to use
  • Some personal issues on the approach to use
  • No suggested changes to our processes, keep a small number of stories for the sprint


Ken H


Lora


Mary


Tom


Tyler


Wayne

  • We accomplished our goals for this sprint!
  • We went one week over our time box, but we expected that to happen and should plan for more time in Sprint 3 to avoid going over again
  • We want to do Agile but do not want to follow Agile practices
  • The entire team needs training on how to properly use the X-Ray plug-in in Jira to create test cases, test executions, report defects, and test fixes to defects