You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

  • Lora and Joel are NOT receiving emails from TSSG-Web.  Invites to the group resent to fix this absence.
  • Jira issue TWS-13 is being used as Epic for MVP release
    • Current target is May 21, 2018
    • There are issues added for parts of MVP that need to be done
  • Lora is moving off from Web team as of May 21, so that has to be our target date for sprint 1
    • No replacement product owner has been lined up yet
  • Not all of the work needed for MVP has been captured yet in a Jira ticket
  • Team Page content is captured in Confluence
  • Joel's wireframes are what the team will be using for the MVP release
    • One wireframe for main page and one wireframe a generic team section
    • Wireframes need to be exported from Google Draw Doc they are currently stored into PDF/PNG files and added into Confluence
  • Team decision: for MVP, single page where the General Meeting section at the top, then a section for each team.
    • Links in navigation bar take you to the part of the page for that team
  • Header and navigation bar remains at top of page as content is scrolled down.
    • Can jump to any section from link in navigation bar
  • No labels